Eskom’s Medupi Unit 5 reaches commercial operation

Featured

Eskom’s Medupi Unit 5 reaches commercial operation Eskom’s Medupi Unit 5 reaches commercial operation

State-owned power utility Eskom announced on Monday that Unit 5 at the Medupi coal-fired power station project, in Limpopo, has reached commercial operation.

“Commercial operation status ensures technical compliance to statutory, safety and legal requirements. This signatory milestone marks the contractual handover of the unit from the primary contractors to Eskom, which means that Medupi Unit 5 is now part of the Eskom generation fleet,” interim group CEO Matshela Koko said in a statement.

Unit 5 achieved successful synchronisation on September 8 and, following further testing and optimising, its full power of 800 MW was attained on December 17, 2016.

Medupi Unit 6 became commercially operational on August 23, 2015.


 

Source

EngineeringNews

back to top

Industries

About us

Follow us

Follow us @BusinessNewsCT

BusinessNewsCT Listeriosis outbreak hits Tiger Brands for R363 million – and counting - https://t.co/8JMSSgk8Sm https://t.co/I311GaGHWc
3hreplyretweetfavorite
BusinessNewsCT Molefe to cut 'deep claws' of corruption at Transnet - https://t.co/dZ2JZOhyHq https://t.co/zCZ9MUrq79
3hreplyretweetfavorite
BusinessNewsCT Molefe to cut 'deep claws' of corruption at Transnet - https://t.co/dZ2JZOhyHq https://t.co/Lrh6Ljg9U5
3hreplyretweetfavorite