Eskom's Sere wind farm now in full commercial operation

Eskom's Sere wind farm now in full commercial operation [Image: mybroadband.co.za]

The Sere wind farm from Eskom recently achieved its full commercial operational capacity of a 100MW. The achievement of this milestone in the Western Cape is in line with the commitments made by Eskom in terms of both time and cost. The African Development Bank approved in 2011 a USD45m loan with USD50m contribution from the Clean Technology Fund, one of the Climate Investment Funds (CIF) for this first utility scale renewable energy project. The World Bank and the French Development Agency also contributed to the financing of the project.

Brian Molefe, Eskom's Acting Chief Executive, said, “Sere is Eskom's first large-scale renewable energy project, and forms part of our commitment to renewable energy and reducing our carbon footprint. The Sere plant adds 100 MW to the national power grid and contributes to saving nearly 6 million tons of greenhouse gas emissions over its 20 years' expected operating life, with average annual energy production of about 298,000MWh, enough to supply about 124,000 standard homes.”

All 46 wind turbines have been erected and energised, and the construction of the new Skaapvlei substation and a 44km 132kV distribution line has been completed. The first wind turbine at the farm was erected in December 2013. The project took the first step towards the goal of synchronising the wind turbines to the grid when the first string of 7 turbines were energised in October 2014. Although Sere had been completely energised and feeding power to the grid since December 30, 2014, the first quarter of 2015 was used to ensure that the milestone of commercial operation is achieved.

Alex Rugamba, Director of the Energy, Environment and Climate Change Department at the AfDB, said, “The project is one of the largest wind energy projects in South Africa. This wind energy facility is comparable to any in the world with regard to cost, time, and quality. It illustrates AfDB's commitment in supporting Africa's transition to green growth and to address the challenges of climate change.”

The wind farm is not the only green energy initiative at Eskom, which is also developing a 100MW concentrating solar plant (CSP) project near Upington in the Northern Cape, a project that will save about 450,000 tons of carbon dioxide emissions over its lifetime. The AfDB is also financing the project with the Clean Technology Fund. The financing is part of loan agreements of USD365m signed in 2011 (USD265m from AfDB's own resources and USD100m from the Clean Technology Fund) to finance Eskom wind and solar utilities.

back to top

Industries

About us

Follow us

Follow us @BusinessNewsCT

BusinessNewsCT My week on Twitter 🎉: 2 Mentions, 4.33K Mention Reach, 1 Like, 2 Retweets, 4.93K Retweet Reach. See yours with… https://t.co/WW4pGraRUG
3hreplyretweetfavorite
BusinessNewsCT Listeriosis outbreak hits Tiger Brands for R363 million – and counting - https://t.co/8JMSSgk8Sm https://t.co/I311GaGHWc
BusinessNewsCT Molefe to cut 'deep claws' of corruption at Transnet - https://t.co/dZ2JZOhyHq https://t.co/zCZ9MUrq79