Good progress being made on Maalgate Bridge Project, George

GOOD progress is being made on the Maalgate Bridge Project outside George in the Southern Cape. This R57-million project saw the replacement contractor appointed in June 2024 and the current anticipated completion date is towards the end of August 2025.ย 

The specific objective of the project is to widen the existing narrow bridge over the Maalgate River on the downstream side.

โ€œThe project faced a number of challenges which included the initial contractor being terminated due to contractual issuesโ€, said Jandrรฉ Bakker, acting director of operational support at the Western Cape Department of Infrastructure.ย 

โ€œWe are, however, pleased to announce that since the appointment of the replacement contractor, matters have been progressing well, and we remain optimistic that the project will be completed according to the agreed programme. The existing Bridge No. 2221 is located at km 15.1 on Trunk Road 2 Section 9 (TR2/9), better known as the R102 airport road near George in the Garden Route District Municipality, is a vital alternative route between Mossel Bay and Georgeโ€, Bakker added.

Provincial Minister of Infrastructure, Tertuis Simmers, recently visited the site as part of his oversight responsibilities during the Premierโ€™s Cycle Tour.

โ€œI am pleased with the progress since the appointment of the replacement contractorโ€, said Simmers. โ€œThe replacement contractor was given the task to create 5 800 person daysโ€™ work, and they have already achieved 8 968. Of the targeted 50 work opportunities, this translated to 62 already achieved. Of the target of R8 445 053,70 to be spent on targeted enterprises, R3 096,178,45 has already been achieved.โ€

โ€œI was recently updated on the technical details of the project. The bridge is an at-grade structure which functions to span the Maalgate River below, which flows in a north-south direction. The existing bridge is a three-span reinforced concrete arch bridge with spandrel walls. The arches are filled with crushed-stone (rock fill), road layer works and an asphalt surfacing on top. The widening of the bridge was designed to match the aesthetics of the original bridge, which was constructed in 1938,โ€ Simmers added.

To enquire about Cape Business News' digital marketing options please contact sales@cbn.co.za

Related articles

If the prime lending rate is phased out, what does it mean for consumers?ย 

If the prime lending rate is phased out, what does it mean for consumers?ย  By Therese Grobler, Head of Wealth Management at Momentum Financial Planning For...

How to Use a Voltage Tester: An Essential Guide for Electrical Safety and Efficiency

How to Use a Voltage Tester: An Essential Guide for Electrical Safety and Efficiency Fluke Electrical Application Note ย ย ย ย  Voltage testers are valuable tools for professionals...

MUST READ

SEW-Eurodrive sets the pace with power packs in African mining

SEW-Eurodrive sets the pace with power packs in African mining Comprehensively supporting the mining sector with commodity-specific drive train solutions, SEW-EURODRIVE has cemented its reputation...

RECOMMENDED

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.