25 air compressors within 4 days. A successful emergency support hire solution from Rand Air

WEDNESDAY 24 January, 2024 was a usual busy day at Rand Air with machine hires going in and out of the yard in Jet Park, Johannesburg, when a frantic call came in from a prominent platinum mine near Rustenburg in the North West Province, urgently requesting 12 000 cfm (cubic feet per minute) of compressed air to keep their underground mining operations going. 

 The mine had experienced a breakdown of their air compressor, subsequently halting production. The compressor supplies critical air to power pneumatic equipment underground.

 Understanding that every hour of down time incurs significant losses for the mine, the proficient Rand Air team, coordinated by Yolande Schmidt, internal sales, immediately flew into action. Sixteen high pressure oil-injected diesel compressors of varying sizes allocated to the project, were inspected by the service team and transported to site where they were connected to the mine’s main air supply line by a Rand Air service technician. Within 24 hours the units were fully operational, constricting the amount of downtime.

 Tshepo Mashaba, external sales at Rand Air, points out that the air has to travel a great distance from the surface to reach the underground equipment so it is absolutely critical to correctly spec the compressors to eliminate potential pressure drops and loss in air flow. 

“Hence we provided a combination of 800 cfm, 1 000 cfm and 1 200 cfm machines to meet these requirements. Our service technician also visited the mine site daily to ensure that all sixteen compressors were running smoothly.”

On 28 January, having suffered yet another breakdown, the mine reached out to Rand Air, requesting a further 14 000 cfm in order to maintain production.

“Undeterred by the fact that it was a Sunday, the well-oiled Rand Air team did not miss a beat,” says Schmidt. 

“It so happened that we had just recently received a consignment of brand new PTS916 air compressors. We got nine of these fresh-off-the-container 1600 cfm units to site and operational for our mine customer within a 24 hour turnaround time.”

To enquire about Cape Business News' digital marketing options please contact sales@cbn.co.za

Related articles

Water independence starts with what you can deploy tomorrow

Water independence starts with what you can deploy tomorrow By Dawid Bredenkamp AS pressure on water resources continues to grow, flexibility is becoming less of a...

Commercial solar battery storage: NID project shows value of peak demand management

Commercial solar battery storage: NID project shows value of peak demand management By Kris van der Bijl A 100kWh battery might seem modest alongside a 1MWp...

MUST READ

ISA releases inventory of R395 billion in infrastructure projects

ISA releases inventory of R395 billion in infrastructure projects Infrastructure South Africa (ISA) has released the third edition of South Africa’s Construction Book - a...

RECOMMENDED