Eskom lays out on transmission expansion

Eskom Managing Director of Transmission,ย Segomoco Scheppers, says the power utility is working hard to expand transmission lines and unlock future generation capacity for the power grid โ€œas fast as possibleโ€.

He was addressing the Transmission Development Plan (TDP) Implementation Forum held at the Eskom Academy of Learning on Wednesday.

Previously, the power utility said it needed to augment the transmission network by approximately 14 200km by 2032 to ensure energy security in the country.

โ€œ[There] are currently 46 expansion projects in execution, of which 26 will deliver 1 632km of transmission lines, 11 290MVA and enable over 15 000MW of generation capacity. Of these 26 projects, 50% will deliver 890km of transmission lines, 3 290MVA of transformer capacity and enable the safe and reliable operation of over 10 000MW of new generation.

โ€œThis includes specifically Medupi and Kusile [power stations] as well as the Garob 267MW project connecting at Kronos substation in the Northern Cape. The other 50%… are in different phases of procurement and will deliver 435km and 8 000MVA, enabling 4 975MW of new generation capacity, mainly in the Northern and Western Cape,โ€ he said.

Scheppers assured the forum that Eskom is โ€œvery focused on ensuring that we expand the grid as fast as possible, while safely managing the power systemโ€.

Into the future

Looking into the future of Eskom transmission, Scheppers said Eskom has approved โ€œthe execution of R26 billion in capital investmentโ€ for transmission, with two priority programmes already in the pipeline to โ€œaccelerate the delivery of the transmission infrastructureโ€.

โ€œThese programmes entail, firstly, the development of 25 projects in existing substationsโ€ฆ which will unlock 13 000MW of new generation in the next five years; secondly, 22 expedited transmission projects that will unlock 24 000MW of grid connection capacity by 2033.

โ€œWe are developing these 47 projects, which have the potential to unlock 37 000MW of grid connection capacity between 2025 and 2033. These projects are at different stages of implementation in terms of design, procurement and construction,โ€ he said.

Scheppers called on all stakeholders to support the power utility in its plans.

โ€œI cannot overemphasise the fact that the successful roll out of our plans will require continued support from all key stakeholders, including relevant authorities unlocking bottlenecks, as well as the market in terms of construction, contractors, suppliers and consultants.

โ€œWe are very grateful for the various NECOM [National Energy Crisis Committee] initiatives, which are proving very effective in addressing some of our historical challenges,โ€ he said.

National Transmission Company SA

Scheppers gave the forum an update on the legal separation of Eskom into the Generation, Distribution and Transmission entities.

According to Scheppers, the separation of transmission entity โ€“ dubbed the National Transmission Company South Africa SOC Ltd (NTCSA) โ€“ is fully underway.

โ€œWe are in the process of getting final approval from the Minister of Public Enterprises for the independent board of directors for this new company. A binding merger agreement has already been signed with suspensive conditions to be fulfilledโ€ฆ in order to transfer the current transmission business into the new subsidiary.

โ€œFollowing the fulfilment of the suspensive conditions, NTCSA will then be operationalised and employees transferred to the new company on the same conditions of service and without disrupting their years of service. We are busy with the lender engagements that are required for us to obtain consent, and these are already at an advanced stage,โ€ he said.

The National Energy Regulator of South Africa (NERSA) has already approved licences for operating the transmission system, trading in electricity, and for import and export.

โ€œThe final licences and associated conditions are being finalised and in fact, we expect that weโ€™ll be in possession of these licences before the end of this month,โ€ he said. โ€“ย SAnews.gov.za

To enquire about Cape Business News' digital marketing options please contact sales@cbn.co.za

Related articles

Cape Town 500MW electricity tender opens door to private power traders

Cape Town 500MW electricity tender opens door to private power traders By Kris Van Der Bijl CAPE Town is three weeks from the closing date on...

Women in Green Building Competition 2026: Your Perspective Matters

Women in Green Building Competition 2026: Your Perspective Matters The Green Building Council South Africa (GBCSA), in partnership with the International Finance Corporation (IFC), invites...

MUST READ

Electric truck market in South Africa needs government action to grow

Electric truck market in South Africa needs government action to grow By Adrian Ephraim SOUTH Africaโ€™s commercial vehicle sector has a policy challenge. The technology for...

RECOMMENDED

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.