Gensets beat outage deadline

“WITH our design and manufacturing experience, we can provide genset solutions that can be started up prior to an outage, so that the plant can continue operating seamlessly while switching from utility to standby power, and back again to the utility,” says Damian Schutte, electrical engineering team leader at Zest WEG.

For a recent project in the Western Cape, the Zest WEG team provided a plant to a customer in the marine sector with a customised genset solution to suit its specific needs. The plant was experiencing considerable downtime due to loadshedding by the national utility, as it would take some time to bring the plant back to operation. The engineered solution includes six 550 kVA generators, two 11 kV transformers, medium-voltage (MV) switchgear, and breakers for synchronising between generators themselves and also with the utility. “The smaller size of generator provides flexibility and is a cost saving, as some units can be switched off depending on the site load requirement,” explains Damian.

Urgent solution

When frequent loadshedding was suddenly announced by the utility, the customer asked Zest WEG for an urgent temporary solution while continuing to implement the project. The team brought three of the gensets on-stream to keep the plant functional until the planned solution was in place.

All major components for power plant solutions such as these can be manufactured and assembled by Zest WEG and Brazil based parent company, WEG. The company can, however, accommodate a client’s specifications should they refer to a nominated supplier, allowing the gensets to be built for easier on-site installation.

“Our extensive engineering and programming on these systems makes it vital that they are fully tested before being delivered to site,” Damian concludes. “Whatever we specify in the contract can usually be tested in-house at our advanced facility in Cape Town.”

Customers are invited to attend the factory acceptance test (FAT), which includes load testing of the generators at different loads up to 110%, synchronisation checks, and MV tests if this is part of the scope.

For more information visit: www.zestweg.com

 

To enquire about Cape Business News' digital marketing options please contact sales@cbn.co.za

Related articles

Africa Energy Indaba 2025: The platform to end load shedding and protect businesses from its impact

LOAD shedding remains one of the biggest challenges affecting African economies, businesses, and livelihoods. As energy disruptions continue to hinder growth and productivity, the Africa...

The suspension of loadshedding has surpassed the 250-day mark, resulting in year-on-year diesel savings of R16.99 billion

The investment in the Generation Recovery Plan continues to yield consistent results, with loadshedding suspended for 254 consecutive days since 26 March 2024. This...

MUST READ

City delivering real change

Behind every budget line, every policy, and every project there are real people, real challenges, and a shared future we are shaping. In a...

RECOMMENDED

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

If you disable this cookie, we will not be able to save your preferences. This means that every time you visit this website you will need to enable or disable cookies again.