Pretoria Workshop delivers first-of-its-kind pulverized fuel burner openings assembly for Duvha Power StationĀ 

Steinmüller Africa successfully ensured uninterrupted operations of Mpumalanga’s Duvha Power Station during its planned maintenance outage in November this year. This was made possible by completing five pulverized fuel burner openings at the company’s Pretoria Workshop.Ā 

The project commenced in May 2024. This involved the detailed prototyping of the various burner components, each meticulously designed to meet precise specifications. To meet the stringent quality standards within the time frame required by Duvha Power Station, the Pretoria Workshop relied on its team of experts in tube rolling and bending, project planning, boiler making, and welding.Ā 

The tubular designs required intricate tube rolling and bending. To ensure the precise angles, diameters, and structural integrity were achieved, advanced machinery and specialised equipment were used. By leveraging the Pretoria Workshop’s in-house capabilities, material integrity was preserved and timely delivery for the planned outage was achieved.Ā 

Using robust project planning tools, the Pretoria Workshop optimised material use from sheet metal layout to cutting and shaping. As a result, the team significantly reduced offcuts and minimised waste. Additionally, the number of butt welds, typically time-intensive and requiring extra material, was reduced.

The manufacturing process also required high-precision boiler making. The boilermakers fabricated the components with meticulous attention to the burner’s precise requirements. Strong, durable welds designed to withstand high temperatures and pressure were then created.

Each weld was inspected to ensure it met safety and quality standards, as these burners will be in demanding operating conditions at the power station.Ā 

ā€œThis project marks a significant milestone for Steinmüller Africa’s Pretoria Workshop by showcasing the capabilities of our team of experts in executing complex, high-precision manufacturing,ā€ says Thabang Kubeka, Project Manager, Steinmüller Africa.

The experts responsible for this project include boilermaker Hudson Chikwature, welding specialist Willem Pelser, and bending foreman Mike McKenna.

ā€œThis success paves the way for the Pretoria Workshop to take on more ambitious projects in the future,ā€ says Kubeka, who adds that the completion strengthens Steinmüller Africa’s role as a trusted partner in supporting Eskom’s operational excellence and reliability at Duvha Power Station, contributing to South Africa’s critical energy infrastructure.

To enquire about Cape Business News' digital marketing options please contact sales@cbn.co.za

Related articles

Water independence starts with what you can deploy tomorrow

Water independence starts with what you can deploy tomorrow By Dawid Bredenkamp AS pressure on water resources continues to grow, flexibility is becoming less of a...

Commercial solar battery storage: NID project shows value of peak demand management

Commercial solar battery storage: NID project shows value of peak demand management By Kris van der Bijl A 100kWh battery might seem modest alongside a 1MWp...

MUST READ

ISA releases inventory of R395 billion in infrastructure projects

ISA releases inventory of R395 billion in infrastructure projects Infrastructure South Africa (ISA) has released the third edition of South Africa’s Construction Book - a...

RECOMMENDED