Record year for private power plants, but signed electricity deals wait on paperwork

Record year for private power plants, but signed electricity deals wait on paperwork

South Africa is on course for a record year of new private power plants, according to the Power Futures Lab at the UCT Graduate School of Business. But a company that has signed a deal to buy electricity from one of these plants cannot start using it until Eskom or the local municipality has signed off the paperwork. In the experience of Open Access Energy, a Cape Town electricity transactions company, how long that takes depends on how prepared the buyer is, where its site is connected to the grid and how well it has been briefed.

Private power producers brought 1,920 MW of new plants online in the first half of 2026, more than in any previous full year. The record until then was 1,472 MW, set in 2016. Ten of those 17 projects, totalling 1,046 MW, sell their electricity directly to mines and factories.

Another 28 projects totalling 2,202 MW are expected by the end of the year.

In its August 2026 briefing note, the Power Futures Lab said some projects may be taking longer to clear their final commercial and grid connection steps, and developers reported delays at Eskom’s grid access office and the National Transmission Company South Africa.

Most of these deals use wheeling. The plant feeds its electricity into the national grid, and the buyer, which may be hundreds of kilometres away, receives a credit on its electricity bill for the same amount. For this to work, two contracts must be in place. The power producer needs an agreement with Eskom or the municipality to use its power lines, called a Use-of-System Agreement. The buyer must also change its existing supply contract with Eskom or the municipality, called an Electricity Supply Agreement.

Until both are signed, the plant cannot be paid for the electricity it was built to sell. Open Access Energy estimates that a 50 MW solar plant selling electricity at R1 a kilowatt-hour earns more than R8-million a month, so every month of delay pushes that income back. That is about R17-million a month for every 100 MW. Across the 1,046 MW of privately contracted plants that started operating in the first half of 2026, a one-month delay would hold back about R170-million.

Open Access Energy has launched a Utility Concierge Service for companies that produce or sell electricity. The service handles the applications and contracts with Eskom and the municipality on the seller’s behalf and follows them through until the electricity is flowing. This includes virtual wheeling, where one plant’s output is credited across many of a buyer’s sites.

The seller’s team no longer has to chase Eskom or the municipality, and the deal can start earning as soon as the contracts are signed. Applications most often get stuck because a letter authorising someone to act for the power producer has not been signed, because documents name different companies, because contracts no longer match the municipality’s latest rules, or because Eskom has asked for information, such as how the electricity is split between sites, that nobody has supplied.

The buyer’s side is often where a deal gets stuck. Sellers usually leave the buyer’s supply contract to the buyer, but few buyers know how to change it, how their Eskom deposit will change or how to prepare the three-year forecast of the electricity they expect to receive, which Eskom asks for.

For buyers supplied directly by Eskom, every site must also be listed on the power producer’s agreement with Eskom, with each site’s share of the electricity adding up to 100%. The service works through these changes with the buyer until they are signed, so the buyer is not left waiting. When a tariff or rule changes, clients can ask Open Access Energy to explain it directly to their buyers.

“There is no fixed timeline,” said Open Access Energy CEO Gerjo Hoffman.

“It depends on how ready the customer is, where they are connected and how well they have been briefed. What we can do is make the process work, because our team knows who to speak to at Eskom and the municipality. All of this is new. There are no written guidelines yet, and Eskom and the municipalities are often working it out as they go. When the rules keep changing, the seller has to keep going back to the buyer with new information, the buyer cannot make a decision, and trust breaks down.

“We sit between them as a neutral party. We explain to the buyer how the process actually works and what they need to do. That takes the operational load off the seller and keeps the deal moving,” said Hoffman.

Research firm Krutham raised the same problem in October. In a submission to the Department of Electricity and Energy, it said the government’s plan to open up the electricity market did not deal with the obstacles to wheeling, including rigid requirements for grid connections, network contracts and supply agreements that discourage investment. It proposed that Eskom and the National Energy Regulator of South Africa fix them by December.

Open Access Energy does not own, trade or sell electricity and is not part of Eskom or any municipality, so it does not take sides between the seller and the buyer. Its job is to get the contracts signed.

Companies that have signed a deal to sell electricity and are waiting on Eskom or a municipality can contact the Utility Concierge Service at hello@openaccess.energy 

To enquire about Cape Business News' digital marketing options please contact sales@cbn.co.za

Related articles

South African wholesale electricity market faces 2027 test

South African wholesale electricity market faces 2027 test South Africa’s wholesale electricity market will open in stages from 2027, turning power into a tradable financial...

Partnerships that power a new energy future

Partnerships that power a new energy future SOUTH Africa’s energy transition will not be delivered by technology alone. It will require partnerships between businesses, energy...

MUST READ

Cape Town Container Terminal boosts deciduous fruit export readiness with R83...

Cape Town Container Terminal boosts deciduous fruit export readiness with R83 million equipment investment With South Africa's deciduous fruit export season underway, the Cape Town...

RECOMMENDED